A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
A. internal project team.
B. key stakeholders.
C. affected team members.
D. full project team.
A. internal project team.
B. key stakeholders.
C. affected team members.
D. full project team.