CompTIA Project+ PK0-004 – Question156

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

A.
Time
B. Schedule
C. Scope
D. Cost

Correct Answer: D