A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
A. Time
B. Schedule
C. Scope
D. Cost
A. Time
B. Schedule
C. Scope
D. Cost