A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?
A. Resource loading
B. Resource leveling
C. Prioritizing tasks
D. Allocating resources
A. Resource loading
B. Resource leveling
C. Prioritizing tasks
D. Allocating resources