CompTIA Project+ PK0-004 – Question158

Which of the following would indicate a project manager is working in a matrix-based organization?

A.
The project manager has full authority over resources and the project.
B. The project manager has no authority over the project resources and limited-to-no authority over the project.
C. Resources align to the project, report to the project manager, and have no functional home at the end of the project.
D. Resources report to business area functional managers and return to the functional area at the end of the project.

Correct Answer: A