Tag: Question 164

CompTIA Project+ PK0-004 – Question164

A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?

A.
Initiation
B. Planning
C. Monitor and control
D. Closing

Correct Answer: D

Tagged CompTIA Project+ PK0-004, Question 164