Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time.
Starting Task B prior to Task A completing is an example of:
A. Managing change
B. Fast tracking
C. Rolling wave planning
D. Crashing
Starting Task B prior to Task A completing is an example of:
A. Managing change
B. Fast tracking
C. Rolling wave planning
D. Crashing