The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?
A. Personal preferences and message content
B. Level of message/report detail and confidentiality constraints
C. Time zones and language barriers
D. Technological and criticality factors
A. Personal preferences and message content
B. Level of message/report detail and confidentiality constraints
C. Time zones and language barriers
D. Technological and criticality factors