A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?
A. Crashing the schedule
B. Prioritizing tasks
C. Determining milestones
D. Developing sprints
A. Crashing the schedule
B. Prioritizing tasks
C. Determining milestones
D. Developing sprints