In which of the following situations is a project manager MOST likely to use a process diagram?
A. When describing a new business idea for the team to review
B. When describing a new business workflow for the team to implement
C. When describing a new business project for the team to implement
D. When describing a new business acquisition for the team to review
A. When describing a new business idea for the team to review
B. When describing a new business workflow for the team to implement
C. When describing a new business project for the team to implement
D. When describing a new business acquisition for the team to review