CompTIA Project+ PK0-004 – Question227

An organization has determined that all projects must use a remote dashboard to allow portfolio management.
Which of the following would enforce this directive?

A.
Project management office
B. Project sponsor
C. Project manager
D. Project coordinator

Correct Answer: A