Which of the following risk strategies prevents a risk from impacting a project?

A.
Accept risk
B. Mitigate risk
C. Avoid risk
D. Transfer risk

Correct Answer: C

Explanation:

Reference: https://pm4id.org/chapter/11-2-risk-management-process/