CompTIA Project+ PK0-004 – Question232 Which of the following risk strategies prevents a risk from impacting a project?A. Accept riskB. Mitigate riskC. Avoid riskD. Transfer risk Show Answer Hide Answer Correct Answer: C Explanation: Reference: https://pm4id.org/chapter/11-2-risk-management-process/