Skip to content

CompTIA Project+ PK0-004

  • CompTIA Project+ PK0-004

Tag: Question 233

CompTIA Project+ PK0-004 – Question233

An active project has a CPI of 0.92. Which of the following can be determined?

A.
The project is currently over budget.
B. The project has a budget surplus.
C. The project is ahead of schedule.
D. The project is behind schedule.

Correct Answer: A

Explanation:

Reference: http://smallbusiness.chron.com/project-management-cpi-numbers-mean-…

Tagged CompTIA Project+ PK0-004, Question 233
Exam Practice Tests

Please disable your adblocker or whitelist this site!