CompTIA Project+ PK0-004 – Question300

Despite receiving regular updates, a sponsor learns a project recently slipped.
Which of the following documents can the sponsor review to determine the project's performance? (Choose two.)

A.
Status report
B. Communication plan
C. Issue log
D. Project schedule
E. Action items list
F. Risk register

Correct Answer: AC