CompTIA Project+ PK0-004 – Question309

A project manager is determining a project's critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)

A.
Costs
B. Dependencies
C. Schedules
D. Durations
E. Holidays
F. Milestones

Correct Answer: BD