CompTIA Project+ PK0-004 – Question350

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

A.
Analyze the critical path and update the WBS with the new feature
B. Add the new feature and reprioritize the product backlog
C. Add the new feature to the next sprint and move the old feature to the following sprint
D. Conduct a retrospective with the team to discuss the change and introduce the feature

Correct Answer: C