CompTIA Project+ PK0-004 – Question366

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?

A.
Five days
B. Six days
C. Seven days
D. Eight days

Correct Answer: B