CompTIA Project+ PK0-004 – Question367

A PM is asked to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information?

A.
Status report
B. Meeting minutes
C. Dashboard
D. Email

Correct Answer: D