Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A. Create a Gantt chart of the milestones
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register
A. Create a Gantt chart of the milestones
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register