In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
A. a dedicated resource pool
B. an allocated resource pool
C. a shared resource pool
D. a benched resource pool
A. a dedicated resource pool
B. an allocated resource pool
C. a shared resource pool
D. a benched resource pool