CompTIA Project+ PK0-004 – Question402

After SOW and contract approvals, the project manager plans to schedule a meeting with the business analyst and several end users. The project manager's main objective in this meeting is to:

A.
identify resources
B. baseline the schedule
C. create deliverables
D. define requirements

Correct Answer: D