The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?
A. Gantt chart
B. Scatter chart
C. Run chart
D. Process diagram
A. Gantt chart
B. Scatter chart
C. Run chart
D. Process diagram