CompTIA Project+ PK0-004 – Question459

Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?

A.
PO numbers
B. Cost baseline
C. Bill of materials
D. WBS codes

Correct Answer: D

Tagged CompTIA Project+ PK0-004, Question 459