A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?
A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget
A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget