A highly skilled project engineer will be on indefinite medical leave. No one on the project team has the required skill set to replace the engineer.
Which of the following will be impacted MOST by the absence of the engineer?
A. Resources
B. Environment
C. Deliverables
D. Requirements
Which of the following will be impacted MOST by the absence of the engineer?
A. Resources
B. Environment
C. Deliverables
D. Requirements