CompTIA Project+ PK0-004 – Question514

A project team is creating a new product, and stakeholders are having a hard time understanding the product.
Which of the following should be sent to the stakeholders?

A.
Printed sketches and potential uses
B. Memo outlining high-level requirements
C. Sponsor mandate for the product
D. Link to the project's intranet site to review status reports

Correct Answer: A