Tag: Question 524

CompTIA Project+ PK0-004 – Question524

Which of the following project management roles is responsible for estimating the duration of tasks?

A.
Project scheduler
B. Project team
C. Project manager
D. Project coordinator

Correct Answer: C

Explanation:

Reference: https://activecollab.com/blog/project-management/project-manager-ro…

Tagged CompTIA Project+ PK0-004, Question 524