CompTIA Project+ PK0-004 – Question551

A customer has requested a change in an active project.
Which of the following actions should the project manager take FIRST?

A.
Gather input from the team.
B. Inform the end user of the change.
C. Submit the change request to the project sponsor.
D. Update the change log.

Correct Answer: C