On larger projects, a vendor may occasionally proceed upon receipt of the:

A.
ROE.
B. RFI.
C. NDA.
D. LOI.

Correct Answer: D

Explanation:

Reference: https://www.investopedia.com/terms/l/letterofintent.asp