A project manager needs to determine resource availability to assign the resources to project tasks.
Which of the following will the project manager MOST likely use?

A.
Resource calendars
B. Project calendar
C. Staffing management plan
D. Conflict resolution

Correct Answer: A

Explanation:

Reference: https://www.float.com/resources/guide-to-resource-calendars/

Tagged CompTIA Project+ PK0-004, Question 575