CompTIA Project+ PK0-004 – Question578

A project team is unable to meet at the same time, thus requiring project work handoff at each shift.
Which of the following constraints might the project team be facing?

A.
Geographic separation
B. Technology limitations
C. Language barriers
D. Personal preferences

Correct Answer: A