CompTIA Project+ PK0-004 – Question583

Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?

A.
Supply Ann with the requested tablet.
B. Have Ann submit a change request.
C. Provide Ann with a copy of the project management plan.
D. Inform Ann that she will receive what has been authorized.

Correct Answer: A