A company is about to initiate a cybersecurity project. However, the project manager realizes the company does not possess the required skills to complete the project and requires a search by third-party vendors.
Which of the following documents should the project manager provide?
A. RFI
B. LOI
C. RFP
D. RFQ
Which of the following documents should the project manager provide?
A. RFI
B. LOI
C. RFP
D. RFQ