CompTIA Project+ PK0-004 – Question592

An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project.
Which of the following is the obstacle?

A.
Ability to identify approval authority
B. Incomplete change control documentation
C. Project team autonomy
D. Change validation process

Correct Answer: D