CompTIA Project+ PK0-004 – Question595

While working on a project, a self-organized team determines what will be accomplished during the next two weeks.
Which of the following describes what the team is doing?

A.
Creating a WBS
B. Gathering continuous requirements
C. Sprint planning
D. Holding a Scrum meeting

Correct Answer: C

Explanation:

Explanation:
A sprint, which is a time-bound period of work, always starts with a sprint planning meeting. During the meeting, team members choose items from the backlog to work on during the sprint. The backlog is a list of requirements (both functional and nonfunctional) for the project. The product owner prioritizes the backlog items based on business need, risk, and value to the organization. The Scrum team members break down large requirements into manageable portions of work that can be completed in a sprint.