A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project.
Which of the following has MOST likely occurred?
A. Scope creep
B. Gold plating
C. Task reprioritization
D. Lack of requirements