A project portfolio will MOST likely align to: A. consumer demand. B. corporate strategy. C. lessons learned. D. PMO guidelines.
Correct Answer: B
Explanation:
Explanation:
Programs and projects within a portfolio are not necessarily related to one another in a direct way. And projects may independently exist within the portfolio (in other words, the project isn’t related to a program but belongs to the portfolio). However, the overall objective of any program or project in a portfolio is to meet the strategic objectives of the portfolio, which in turn should meet the strategic objectives of the business unit or corporation.