CompTIA Project+ PK0-004 – Question614

A sensitive project requires activities to occur with very specific, to-the-minute timing. Which of the following would BEST ensure on-time delivery?

A.
Text messaging
B. Face-to-face activity monitoring
C. Video conferencing
D. Voice conferencing

Correct Answer: C