CompTIA Project+ PK0-004 – Question618

A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned about losing access to the data.
Which of the following documents is appropriate for use in this situation?

A.
Project schedule
B. Risk register
C. Action item log
D. Issue log

Correct Answer: B