During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?
A. Identification
B. Registration
C. Quantification
D. Qualification