CompTIA Project+ PK0-004 – Question634

Which of the following is the burn rate of a project?

A.
The amount of project staff turnover over time
B. The positive cash flow of the project for the organization over time
C. The amount of expenditures supporting the project over time
D. The amount of capital spent to ensure quality of the project deliverables

Correct Answer: C

Explanation:

Explanation:
Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.