A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below:
Which of the following risks from the risk register should have an acceptance strategy? (Choose two.)
A. 1
B. 2
C. 3
D. 4
E. 5
F. 6
Which of the following risks from the risk register should have an acceptance strategy? (Choose two.)
A. 1
B. 2
C. 3
D. 4
E. 5
F. 6