CompTIA Project+ PK0-004 – Question667

A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?

A.
RFI
B. PO
C. RFQ
D. SOW

Correct Answer: A

Explanation:

Reference: https://trainingindustry.com/wiki/outsourcing/request-information-r…