CompTIA Project+ PK0-004 – Question667 A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?A. RFIB. POC. RFQD. SOW Show Answer Hide Answer Correct Answer: A Explanation: Reference: https://trainingindustry.com/wiki/outsourcing/request-information-r…