CompTIA Project+ PK0-004 – Question671 A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?A. SLAB. SOWC. LOID. RFQ Show Answer Hide Answer Correct Answer: C Explanation: Reference: https://en.wikipedia.org/wiki/Letter_of_intent