CompTIA Project+ PK0-004 – Question673

A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?

A.
Project schedule
B. Issue log
C. Risk register
D. Scope statement

Correct Answer: B