Skip to content

CompTIA Project+ PK0-004

  • CompTIA Project+ PK0-004

Tag: Question 679

CompTIA Project+ PK0-004 – Question679

Which of the following project team members is responsible for managing quality assurance?

A.
Project stakeholder
B. Project sponsor
C. Project manager
D. Project scheduler

Correct Answer: C

Explanation:

Reference: https://www.pm4dev.com/pm4dev-blog/entry/who-is-responsible-for-pro…

Tagged CompTIA Project+ PK0-004, Question 679
Exam Practice Tests