CompTIA Project+ PK0-004 – Question693

A project manager realizes there is a significant risk event. Which of the following is the FIRST step the project manager should perform?

A.
Escalate the issue to the sponsor
B. Assign an owner to take action
C. Update the issue log
D. Activate the contingency plan

Correct Answer: A