CompTIA Project+ PK0-004 – Question695

The Chief Executive Officer (CEO) informs the project manager that a project must be completed six months earlier than previously scheduled. Which of the following is the BEST way for the project manager to respond?

A.
Increase the quality parameters.
B. Transfer more productive resources to the project.
C. Recommend a reduction of the deliverables.
D. Update the project scope.

Correct Answer: C