Which of the following indicators will assist the project manager in determining the health of the budget?

A.
SV
B. CPI
C. AC
D. EV
E. ETC

Correct Answer: D

Explanation:

Reference: https://pmstudycircle.com/planned-value-pv-earned-value-ev-actual-c…