CompTIA Project+ PK0-004 – Question716

A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?

A.
Timeline
B. Quality
C. Budget
D. Scope

Correct Answer: A