CompTIA Project+ PK0-004 – Question720

Which of the following is primarily responsible for developing the timeline?

A.
Project sponsor
B. Project coordinator
C. Project manager
D. Project scheduler

Correct Answer: D

Explanation:

Explanation:
The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.”
– Kim Heldman CompTIA Project+ Study Guide; 2nd Edition; Sybex; Indianapolis.